It's amazing how quickly things are moving along. Here are some bullets of other things I noticed that were completed.
- The entire sound/media booth is sheetrocked and looks like it's part of the room now.
- Entire stage is completed, including the closets and the equipment ramp that leads down to the green room back stage.
- All recessed lighting cans are in place throughout the lobby. You can really start to see how this area is going to look!
- All floors have been swept and are being prepped for covering.
Other things that happened last week.
- Our chairs were ordered and will be here right on time!
- Our stage curtains are being designed and are set to be installed exactly on time!
- Our building sign is being finalized and is set to be installed on time.
Check back later this week to see some pictures of the progress!